某二类居住项目提前封闭沉降后浇带分析研究
摘要:北京市大兴区某二类居住用地项目为多栋高层住宅环绕地下车库建筑,为消除差异沉降不利影响,设置了多条沉降后浇带,后浇带的存在严重制约项目工期。根据场地地质条件、地基基础方案以及上部结构荷载分布情况,采用PLAXIS3D进行沉降分析,并结合实际工程经验论证提前封闭沉降后浇带的可行性,结果表明提前封闭沉降后浇带可行。该项目提前封闭了沉降后浇带,实现了预期目的。
Abstract:A Class II residential land project in Daxing District, Beijing is surrounded by multiple high-rise residential buildings and an underground parking garage. To eliminate the adverse effects of differential settlement, multiple post-cast strips were installed. The existence of post-cast strips seriously restricts the project schedule. Therefore, based on the geological conditions of the site, the foundation scheme, and the distribution of loads on the upper structure, PLAXIS3D was used for settlement analysis, and the early closure of settlement post-cast strips was feasibility according to practical engineering experience. The project implemented an early closure of the post-cast strips, thereby accomplishing the intended objectives.
中文标题:
某二类居住项目提前封闭沉降后浇带分析研究
Analysis and Research on Early Closure of Settlement Post-cast Strip for a Type II Residential Land Project
作者:
赵灿1,,张靖一2,王媛2,李伟强2,
Zhao Can1,,Zhang Jingyi2,Wang Yuan2,Li Weiqiang2,
作者简介:赵 灿,男,1986年生,汉族,山东泰安人,硕士,高级工程师,主要从事建筑结构设计研究。E-mail:335742334@qq.com
通讯地址:
1.中铁房地产集团北方有限公司,北京 102442 2.北京市建筑设计研究院有限公司,北京 100045
1.ChinaRailwayConstructionRealEstateGroupNorthCo.,Ltd.,Beijing102442,China 2.BeijingInstituteofArchitecturalDesign,Beijing100045,China
中图分类号:TU470
doi:10.3969/j.issn.1007-2993.2024.04.009
出版物:岩土工程技术
收稿日期:2023-03-10
修回日期:2023-07-14
录用日期:2023-11-08
网络出版日期:2024-08-09
刊出日期:2024-08-09
关键词:沉降后浇带,差异沉降,施工过程,数值模拟,封闭时间
Key words:settlement post-cast strip,differential settlement,construction process,numerical simulation,closing time
文档包含图片数量:图片(7)张
文档包含表格数量:表格(5)个
参考文献:
[1]韩 玲, 李伟强, 徐 斌, 等. 某工程大面积地下室与多高层主楼连成一体的地基基础设计及沉降控制[J]. 建筑结构,2013(S1):204-207.
[2]DBJ 11—501—2009 北京地区建筑地基基础勘察设计规范[S].
[3]GB 50007—2011 建筑地基基础设计规范[S].
[4]刘旭冉, 伊达侯, 春明武, 等. 重庆来福士广场沉降后浇带提前封闭关键技术[J]. 施工技术, 2019, 48(24): 110-112.
[5]鲜林雪, 蒋林哲, 朱晓东. 沉降后浇带提前封闭构造施工技术[J]. 施工技术, 2018, (S4): 321-323.
[6]丁国荣, 王晓锋. 点板式楼座沉降后浇带提前封闭施工技术[J]. 施工技术, 2016, (9): 63-65.
[7]吕正良. 地下室顶板沉降后浇带提前封闭施工技术探究[J]. 房地产世界, 2021, (11): 69-71.
[8]朱 翔, 于海宾, 郭院成, 等. 桩筏基础沉降后浇带浇筑时机研究[J]. 建筑结构,2017(9):85-89.
[9]刘利平, 王 伟, 殷青芳, 等. 基于上部结构–桩筏基础–地基共同作用的地基与基础变形分析[J]. 建筑科学,2014(7):38-43.
[10]王 媛, 李伟强, 孙宏伟. 厚层黏性土地基上某超高层建筑桩筏基础三维数值分析[J]. 建筑结构,2014(20):119-122.
[11]王 媛, 孙宏伟, 方云飞. 数值软件在地基基础沉降变形计算中的应用与实例[J]. 建筑结构,2013,43(22):19-23.
[12]王 媛, 孙宏伟. 北京Z15地块超高层建筑桩筏基础的数值分析[J]. 建筑结构,2013,43(17):26-31.
基金项目:
- 文件大小:
- 2.97 MB
- 下载次数:
- 60
-
高速下载
|
|